ahlfingerzMay 1, 20221 min readWeek 28 ReportThis week, the team assembled the final prototype. Both syringe pumps are mounted to boards and can run with their respective syringes....
ahlfingerzMay 1, 20221 min readWeek 27 ReportThe biggest updated is that we now our pivoting to our second highest Pugh scoring device - the veritical mnp syringe. It will be 1 ml,...
ahlfingerzApr 1, 20221 min readWeek 26 ReportThis week, the team met on Friday to continue working on the prototyping stage of the project. Upon the arrival of new solenoid...
ahlfingerzApr 1, 20221 min readWeek 25 ReportThis week was spring break. The final large purchase was made, that included a force sensor, bubble sensor, and screen. Quinlan updated...
ahlfingerzApr 1, 20221 min readWeek 23 ReportThis week, the group focused on ordering parts for the second iteration of the syringe pump. Since the first prototype is assembled, the...
ahlfingerzApr 1, 20221 min readWeek 22 ReportThis week, the group assembled the first rendition of the system for proof-of-concept testing. Tests included those for the magnets and...
ahlfingerzApr 1, 20221 min readWeek 21 ReportThis week the team finished the first iteration of the dual stepper motor syringe. Missing a key part that was backordered, it works fine...
ahlfingerzApr 1, 20221 min readWeek 20 ReportThis week, the team continued prototyping. Quinn contacted Mike at UNandUP to obtain parts for our open source syringe pump. On Friday,...
ahlfingerzApr 1, 20221 min readWeek 19 ReportThis week, the group began working with the pieces that were 3D printed at the UN&UP office before the group came in to work on the...
ahlfingerzApr 1, 20221 min readWeek 18 ReportThis week, the team met to discuss progress on prototyping. The team meant to go in to start prototyping on the day of the meeting....
ahlfingerzApr 1, 20221 min readWeek 17 ReportThis week, Quinlan outlined all the electronics needed for the first iteration of the dual syringe. The parts where ordered through...
ahlfingerzApr 1, 20221 min readWeek 16 ReportOver winter break, the group discussed the parts that would be ordered for the prototyping to begin. Due to the delay of in-person...
ahlfingerzDec 11, 20211 min readWeek 13 ReportIn week 13, the team met on Monday to discuss design specifications for the progress report. This will help the team in making the...
ahlfingerzDec 11, 20212 min readWeek 12 ReportIn Week 12, the group completed the list of potential solutions to be added to the Pugh Charts and began listing criteria to apply to...
ahlfingerzNov 14, 20211 min readWeek 11 ReportThis week, the team communicated via text this week relaying information from articles on the magnetic particle and infusion pump aspects...